Planning Commission
Abstract
The scheme envisages establishment of (1) Central Power Station at Rangat Day with an installed capacity of 750 KW by adding 3 x 250 KW diesel generating sets (2) Construction of 85 KM H.T. line between Mayabunder and Dakultala (3) extension of existing L.T. line and providing more service connections at Mayabunder and Rangat. With the implementation of this scheme it is expected to meet the power requirement of that area which is estimated to be 559.57 KW and to cover above 31 villages.
Description
Keywords
Citation
Planning Commission- 1974